• There will be a Power Interruption Schedule on Wednesday, September 30, 2015 between 7:00 A.M. to 6:00 P.M. affecting Switch and Sandal Substation.

Area/s Affected:

  • Municipalities of Aurora, Ramon Magsaysay, Sominot, Midsalip, Tambulig, Molave, Mahayag, Dumingag and Josefina, Zamboanga del Sur including Don Victoriano, Misamis, Occidental.

Reason/s of Interruption:

  • The NGCP interruption is to facilitate repair of structure numbers 81-3T, 104-HT, 105-E, 106-B, 97-E, 133-B, 63-3T, 79-3T, 92-3T and 137-B along the above mentioned line.
  • Clearing and cutting of trees along these affected power lines.

Power will be restored without prior notice as soon as the construction works are completed. Please advise electric consuming public to take necessary precautions.

Thank You!

(SGD) JOSE RAUL A. SANIEL

General Manager