Please be informed of the power service interruption scheduled on August 27, 2011, Saturday, from 6:00AM to 5:00PM along the Pagadian-San Miguel 69kv Line.
Customers served under ZAMSURECO-I's Sta. Maria, Balangasan and San Miguel Substations will be affected during the entire duration of work while customers served under Tiguma Substation will experience brief power interruptions during switching operations.
Activities will include replacement of rotten poles, cross-arms and corroded insulators at St. Nos. 01-HT, 27-ABS, 28-3T, 29-HT, 104-HS and 214-HS located at Pagadian City and San Miguel, Zamboanga del Sur.
We will resume normal operation immediately after completion of the scheduled work not necessarily following the above given schedule.
Please take the necessary preparations and precautions in anticipation of this scheduled power interruption.
Thank you very much.
(SGD) AVELINO Q. DAWIS
Date received: 08-19-2011