• Please be informed that  NGCP has scheduled power interruption for Pagadian-San Miguel  69KV Line on  Sunday, February 16, 2014 between 8:00 AM to 8:30 A.M.

Area/s Affected:

  • Pagadian City and municipalities of Tukuran, Labangan, Dumalinao, Guipos, San Pablo, Tigbao, Lapuyan, Margosatubig, San Miguel, Vincenzo Sagun, Dimataling, Dinas, Pitogo, Tabina, including brgys Lantungan, Resthouse, Inroad and Lubid, all of Aurora, Zamboanga del Sur.

Reason/s of Interruption Schedules:

  • NGCP will conduct / facilitate the switching procedures for transfer of loads from their old 100MVA ABB Power Transformer to their newly commissioned 100MVA Alstom Power Transformer at Aurora Substation, Cabilinan, Aurora, Zamboanga del Sur.
The NGCP will resume normal operation immediately after completion of the scheduled work.
 
Please advise electric consuming public to take necessary  precautions in anticipation of this scheduled power interruption

Thank you and best regards.

 

(SGD) JOSE RAUL A. SANIEL

General Manager