Please be informed that there will be power interruption on the following schedules:
I. Tuesday, February 17, 2015 between 8:00 A.M. to 12:00 NOON.
Area/s Affected:
Purok Sweet Honey, Sta. Maria District and portion of San Francisco District, Pagadian City
Reason/s of Interruption Schedules:
1.Replacement of two (2) rotten poles with primary lines (A1 and A2 structures) that served the 100 KVA Distribution Transformer.
2. Clearing and cutting of trees along these affected power lines
II. Thursday, February 19, 2015 between 10:00 A.M. to 12:00 NOON.
Area/s Affected:
Purok Rubia and Bay View, Sta Maria, District, Pagadian City.
Reason/s of Interruption Schedules:
1. Erection of pole to correct vertical clearance of primary lines (Pole Number 219041).
2. Clearing and cutting of trees along these affected power lines
Power will be restored without prior notice as soon as the maintenance works are completed.
Thank you and best regards.
(SGD) JOSE RAUL A. SANIEL
General Manager/CEO