Scheduled Power Interruption (SEPTEMBER 15, 2022) between 9:00 AM - 5:00 PM
SCHEDULED POWER INTERRUPTION
Date: SEPTEMBER 15, 2022 (Friday)
Time: 9:00 AM - 5:00 PM
Duration: 8 hours
Affected area/s:
Portion of MUNICIPALITY OF PITOGO, ZDS:
-Brgy. Sugbay Dos
-Brgy. Poblacion Pitogo
-Brgy. Balabawan
-Brgy. Liguac
-Brgy. Panubigan
-Brgy. Balong-balong
-Brgy. Liasan
-Brgy. San Isidro
-Brgy. Lower Panikian
Reason/s of Interruption:
1.Replacement of rotten poles 2-B1, 2-B2, 2-B3 structures and 2-B1 inserted pole due to insufficient height replacement of rotten crossarms.
2.Installation of Sectionalizing Cut-out.
3.Vegetation Clearing along the 3 Phase Backbone Line(5 kms) from Brgy. Sugbay Dos to Brgy. Poblacion Pitogo and (6 kms) from portion of Brgy. Poblacion Pitogo to Brgy. Panubigan V-Phase Line.
As a safety precaution, please always consider the power lines energized during the power interruption. Power will be immediately restored upon completion of the scheduled works. Please take the necessary preparations and precautions in anticipation of this scheduled power interruption.
Thank you
Warning: count(): Parameter must be an array or an object that implements Countable in /home/zamsureco1/public_html/templates/burmont/html/com_k2/templates/default/item.php on line 160
Download attachments:
- IMG-431eb0c86260ac908bc4bf2ae51007bc-V.jpg (363 Downloads)