NGCP Scheduled Power Interruption (September 11, 2022) between 10:00 am - 1:00 pm
NGCP SCHEDULED POWER INTERRUPTION
Date: SEPTEMBER 11, 2022 (Sunday)
Time: 10:00 AM-1:00 PM
Duration: 3 Hours
Affected area/s:
• UPPER BAYAO Substation
• TIGUMA Substation
• STA. MARIA Substation
• BALANGASAN Substation
• SAN MIGUEL Substation
Municipalities affected:
•PAGADIAN CITY
•LABANGAN
•DUMALINAO
•TIGBAO
•GUIPOS
•SAN PABLO
•SAN MIGUEL
•LAPUYAN
•DIMATALING
•DINAS
•VINCENZO SAGUN
•MARGOSATUBIG
•PITOGO
•TABINA
•Portion of AURORA, ZDS
-Brgy. Lubid
-Brgy. Lantungan
-Brgy. Inroad
-Brgy. Resthouse
•Portion of municipality of TUKURAN, ZDS
-excluding brgys:
x Navalan
x Laperian
x Buenasuerte
x Sambulawan
Reason/s of Interruption:
1. NGCP will conduct Manual Load Dropping as contingency measure during the shutdown of Baloi-Agus 5 138kV Line for the replacement of High Voltage Equipment at Baloi Substation.
As a safety precaution, please always consider the power lines energized during the power interruption. Power will be immediately restored upon completion of the scheduled works. Please take the necessary preparations and precautions in anticipation of this scheduled power interruption.
Thank you.
Warning: count(): Parameter must be an array or an object that implements Countable in /home/zamsureco1/public_html/templates/burmont/html/com_k2/templates/default/item.php on line 160
Download attachments:
- IMG-431eb0c86260ac908bc4bf2ae51007bc-V.jpg (363 Downloads)