NGCP Scheduled Power Interruption (May 28, 2023) between 5:00 AM - 5:00 PM
NGCP SCHEDULED POWER INTERRUPTION
Date: MAY 28, 2023 (SUNDAY)
Time: 5:00 AM - 5:00 PM
Duration: 12 HOURS
Affected area/s:
• UPPER BAYAO Substation
• TIGUMA Substation
• STA. MARIA Substation
• BALANGASAN Substation
• SAN MIGUEL Substation
Municipalities affected:
•PAGADIAN CITY
•LABANGAN
•DUMALINAO
•TIGBAO
•GUIPOS
•SAN PABLO
•SAN MIGUEL
•LAPUYAN
•DIMATALING
•DINAS
•VINCENZO SAGUN
•MARGOSATUBIG
•PITOGO
•TABINA
•Portion of AURORA, ZDS
-Brgy. Lubid
-Brgy. Lantungan
-Brgy. Inroad
-Brgy. Resthouse
•Portion of the municipality of TUKURAN, ZDS
-excluding brgys:
x Navalan
x Laperian
x Buenasuerte
x Sambulawan
Reason/s of Interruption:
1. NGCP will conduct transmission line maintenance along Aurora-San Miguel 69kv Line.
As a safety precaution, please always consider the power lines energized during the power interruption. Power will be immediately restored upon completion of the scheduled works. Please take the necessary preparations and precautions in anticipation of this scheduled power interruption.
Thank you.
Warning: count(): Parameter must be an array or an object that implements Countable in /home/zamsureco1/public_html/templates/burmont/html/com_k2/templates/default/item.php on line 160
Download attachments:
- IMG-431eb0c86260ac908bc4bf2ae51007bc-V.jpg (281 Downloads)