SCHEDULE POWER INTERRUPTION (NOVEMBER 13, 2024) between 8:00 AM - 5:00PM
SCHEDULE POWER INTERRUPTION
Date: NOVEMBER 13, 2024 (WEDNESDAY)
Time: 8:00 AM- 5:00 PM
Duration: 9 Hours
Affected Areas:
*Portion of Guipos (Barangay Lower Canunan and Guling)
*Entire Municipality of San Pablo
>including: Barangay Tubo-Pait, Dumalinao.
>Except: Barangay Bagong Misamis, San Pablo and Purok Riverside, Payag, San Pablo.
Reason/s of Interruption:
*ZAMSURECO-I will conduct a replacement of 11 rotten poles (which include 7 pole structures conversion), 7 rotten crossarm and clearing of power lines (approximately 3. 694 circuit kms) at Barangay Payag to Barangay Mabuhay, San Pablo, ZDS. As phase 8 (last power interruption) in preparation for the rehabilitation and conversion of the San Pablo Backbone Line from Vee Phase to Three Phase Primary Line and Reconductoring of Primary Conductors from 2/0 all Aluminum Bare Wire ACSR to 4/0 All Aluminum Bare Wire ACSR.
As a safety precaution, please always consider the power lines energized during the power interruption. Power will be immediately restored upon completion of the scheduled works. Please take the necessary preparations and precautions in anticipation of this scheduled power interruption.
Thank you.
Warning: count(): Parameter must be an array or an object that implements Countable in /home/zamsureco1/public_html/templates/burmont/html/com_k2/templates/default/item.php on line 160