Scheduled Power Interruption (May 6, 2023) between 9:00 AM -11:00 AM
SCHEDULED POWER INTERRUPTION
Date: MAY 6, 2023 (SATURDAY)
Time: 9:00 AM - 11:00 AM
Duration: 2 HOURS
affected substation/S:
• CULO substation
affected entire municipalities:
• MAHAYAG
• DUMINGAG
• DON VICTORIANO
• JOSEFINA
• MOLAVE
AFFECTED AREAS of TAMBULIG:
• BRGY. PELOCUBAN,
• BRGY. BAG-ONG KAUSWAGAN
• BRGY. LIBATO
• BRGY. BAG-ONG TABUGON
• BRGY. LOWER LIASON
• BRGY. UPPER LIASON
•BRGY. UPPER DIMALINAO
AFFECTED AREAS of SOMINOT:
• BRGY. LANTAWAN
• BRGY. NEW OROQUITA
Reason of Interruption:
1. TO CONDUCT INSPECTION ON REPORTED LEAKING INSULATOR
2. MOLAVE FEEDER LINE MAINTENANCE RIDE ON ACTIVITY
A. REPLACE DEFECTIVE CUT-OUT OF CINEMA SQUARE
B.TRANSFER LOAD FROM OLD BACKBONE LINE TO 4/0 BACKBONE LINE
3. MAHAYAG FEEDER LINE MAINTENANCE RIDE ON ACTIVITY:
A. REPLACEMENT OF LEAKING PIN INSULATOR (BACKBONE LINE)
As a safety precaution, please always consider the power lines energized during the power interruption. Power will be immediately restored upon completion of the scheduled works. Please take the necessary preparations and precautions in anticipation of this scheduled power interruption.
Thank you
Warning: count(): Parameter must be an array or an object that implements Countable in /home/zamsureco1/public_html/templates/burmont/html/com_k2/templates/default/item.php on line 160
Download attachments:
- IMG-431eb0c86260ac908bc4bf2ae51007bc-V.jpg (310 Downloads)